For Motor
|
|
Size of Capacitor = 1/3 Hp of
Motor ( 0.12x KW of Motor)
|
|
For Transformer
|
|
< 315 KVA
|
5% of KVA Rating
|
315 KVA to 1000 KVA
|
6% of KVA Rating
|
>1000 KVA
|
8% of KVA Rating
|
Earthing Resistance value:
Earthing Resistance Value
|
|
Power Station
|
0.5 Ω
|
Sub Station Major
|
1.0 Ω
|
Sub Station Minor
|
2.0 Ω
|
Distribution Transformer
|
5.0 Ω
|
Transmission Line
|
10 Ω
|
Single Isolate Earth Pit
|
5.0 Ω
|
Earthing Grid
|
0.5 Ω
|
As per NEC Earthing Resistance
should be <5.0 Ω
|
Voltage Limit (As per CPWD
& Kerala Elect.Board):
Voltage Limit (As Per CPWD)
|
|
240V
|
< 5 KW
|
415V
|
<100 KVA
|
11KV
|
MVA
|
22KV
|
<6 MVA
|
33KV
|
<12 MVA
|
66KV
|
<20 MVA
|
110KV
|
<40 MVA
|
220KV
|
>40 MVA
|
Voltage Variation
> 33 KV
|
(-) 12.5%
to (+) 10%
|
< 33 KV
|
(-) 9% to
(+) 6%
|
Low
Voltage
|
(-) 6% to
(+) 6%
|
Insulation Class:
Insulation
|
Temperature
|
Class A
|
105°C
|
Class E
|
120°C
|
Class B
|
130°C
|
Class F
|
155°C
|
Class H
|
180°C
|
Class N
|
200°C
|
Standard Voltage Limit:
Voltage
|
IEC
(60038)
|
IEC
(6100:3.6)
|
Indian
Elect. Rule
|
ELV
|
< 50 V
|
|
|
LV
|
50 V to 1
KV
|
<=1 KV
|
< 250 V
|
MV
|
|
<= 35
KV
|
250 V to
650 V
|
HV
|
> 1KV
|
<= 230
KV
|
650 V to
33 KV
|
EHV
|
|
> 230
KV
|
> 33 KV
|
Standard
Electrical Connection (As per GERC):
As per Type of Connection
|
|
Connection
|
Voltage
|
LT Connection
|
<=440V
|
HT connection
|
440V to 66KV
|
EHT connection
|
>= 66KV
|
As per Electrical Load Demand
|
|
Up 6W Load demand
|
1 Phase 230V Supply
|
6W to 100KVA(100KW)
|
3 Phase 440V Supply
|
100KVA to 2500KVA
|
11KV,22KV,33KV
|
Above 2500KVA
|
66KV
|
HT Connection Earthing
|
|
H.T Connection’s Earthing Strip
|
20mmX4mm Cu. Strip
|
CT & PT bodies
|
2Nos
|
PT Secondary
|
1Nos
|
CT Secondary
|
1Nos
|
I/C and O/G Cable+ Cubicle Body
|
2Nos
|
Standard Meter Room Size (As
per GERC):
Meter Box
Height
|
Upper
level does not beyond 1.7 meter and Lower level should not below 1.2 meter
from ground.
|
Facing of
Meter Box
|
Meter Box
should be at front area of Building at Ground Floor.
|
Meter Room
/ Closed Shade
|
4 meter
square Size
|
Approximate Load as per Sq.ft
Area (As per DHBVN):
Sq.ft Area
|
Required
Load (Connected)
|
< 900
Sq.ft
|
8 KW
|
901 Sq.ft to 1600 Sq.ft
|
16 KW
|
1601 Sq.ft to 2500 Sq.ft
|
20 KW
|
> 2500 Sq.ft
|
24 KW
|
For Flats
:100 Sq.ft /
1 KW
|
|
For Flats
USS /TC: 100 Sq.ft /
23 KVA
|
Contracted
Load in case of High-rise Building:
For
Domestic Load
|
500 watt
per 100 Sq. foot of the constructed area.
|
For
Commercial
|
1500 watt
per 100 Sq. foot of the constructed area
|
Other
Common Load
|
For lift,
water lifting pump, streetlight if any, corridor/campus lighting and other
common facilities, actual load shall be calculated
|
Staircase
Light
|
11KW/Flat
Ex: 200Flat=200×11=2.2KW
|
Sanctioned Load for Building
|
|
Up to 50 kW
|
The L.T. existing mains shall be
strengthened.
|
50 kW to 450 kW (500 kVA)
|
11 kV existing feeders shall be
extended if spare capacity is available otherwise, new 11 kV feeders shall be
constructed.
|
450 kW to 2550 kW (3000 kVA)
|
11 kV feeder shall be constructed
from the nearest 33 kV or 110 kV substation
|
2550 kW to 8500 kW (10,000 kVA)
|
33kV feeder from 33 kV or 110 kV
sub station
|
8500 kW (10,000 kVA)
|
110 kV feeder from nearest 110 kV
or 220 kV sub-station
|
Great insights on electrical thumb rules! Understanding proper cable selection is crucial, especially for high-voltage applications. I’ve learned that 35KV power cables require careful insulation and installation to handle heavy loads safely. It's amazing how small details can make a big difference in electrical work!